SchedolaProject Controls
Services

5 practices.
One line of sight.

All practices & services →
04 · 7 services

Delay & Claims

Forensic delay analysis, time and money entitlement, and independent expert evidence that holds up under cross-examination.

Open
05 · 7 services

Digital Delivery

BIM, 4D and 5D, reality capture and digital twins, wired into the schedule and the budget.

Open
Featured practice

The finish line, visible from day one.

About Schedola

Clarity is a discipline.

Founded by Colins Epie to give every capital project a clear line of sight to its finish.

Overview
Markets

16 markets. One standard of clarity.

Sector fluency, applied with the same discipline everywhere.

Overview
Projects

$19.56B of capital, in plain sight.

60 featured projects across 17 sectors. Every client confidential.

Overview
Insights

Field notes for people who build.

Research, papers and plain-spoken guidance from our practitioners.

Overview
Careers

Do work you can see finished.

Careers for people who would rather know than hope.

Overview
Representative engagement · Data Centers

Putting a hyperscale campus back on its power date

Every contractor reported float. The energisation date was drifting anyway. One integrated schedule made the real position visible, and a weekly recovery rhythm brought it back.

MarketData Centers
RegionSouthern United States
RoleOwner-side program controls
EngagementRecovery & integrated scheduling
Ref4.3.1
StatusRepresentative
The challenge

Four schedules said on track. The campus disagreed.

The owner of a multi-building hyperscale campus received monthly updates from each of its contractors, and every one showed comfortable float. No one, however, had tested the utility interconnect, switchgear deliveries and commissioning sequence against each other. Leadership could feel the energisation date moving but could not show where, or by how much.

Meetings had become arguments about whose schedule was right. The customer was waiting on capacity, and the owner’s board was waiting on an answer.

Representative engagement. Client identity withheld; specifics anonymised and illustrative.

Our approach

How we changed the outcome

We replaced four competing narratives with one logic-linked schedule, then used it every week to decide what to do next.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Find the real position

Health checks on each contractor schedule exposed open ends, hard-constrained dates and commissioning work that simply was not there.

PHASE 02Join it up

An integrated master schedule linked utility milestones, electrical procurement, construction and Level 1 to 5 commissioning on one critical path.

PHASE 03Plan the recovery

Commissioning was resequenced and equipment release reprioritised, giving the campus a credible route back to its date.

PHASE 04Keep it honest

A weekly recovery review and concise executive reporting held every party to the same plan.

What changed

The difference we made

The owner gained a single forecast it could defend and a recovery plan that every contractor had signed up to.

Result 01One critical path

Leadership could see the whole route from interconnection to integrated systems testing for the first time.

Result 02Earlier warning

Long-lead electrical risk surfaced months sooner, while alternative supply was still an option.

Result 03Decisions, not debate

Executive meetings shifted from disputing data to agreeing actions.

Services engaged
Once everyone was looking at the same critical path, the conversation changed completely.
Client perspective · name withheld for confidentiality
Start with one conversation

See your finish from here.

Tell us where your project stands today. In one conversation with a senior practitioner you will know where it is really heading, what is driving it, and what it will take to land it.

  • Senior practitioner on the first call
  • Confidential by default
  • A straight answer, not a sales pitch