LocationWinnipeg, CanadaFood and beverage plants live by market windows: peak season, retail launches, distribution contracts. Miss the window and the new capacity waits a year to earn its keep.
A food manufacturer modernized one of its largest frozen dessert plants, adding three production lines and an automated cold store.
Any shutdown in peak season meant product missing from stores. Cutovers had to fall in the few low-demand weeks the sales team could spare.
The whole job, on one line.
Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's date.
Our approach, phase by phase.
The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

The difference we made
Measured the only way that matters: did the project land where we said it would.
No production was lost during the peak selling season across the full program.
Every planned shutdown finished inside its window.
Line trials and food-safety sign-offs were built into the logic, not left to the end.
What we brought to it
Hour-by-hour shutdown schedules that shorten outage windows and return critical assets to service safely and on time.
01.18Commissioning & Startup SchedulingSystem-based commissioning and startup schedules that carry facilities from mechanical completion to reliable operation.
01.03Integrated Master Scheduling (IMS)Integrated Master Schedules that connect design, procurement, construction and commissioning into a single program view, traceable from the boardroom summary down to the field.
02.07Progress MeasurementQuantity-based, field-verified progress measurement that turns physical work into data owners and lenders can trust.
More Food & Beverage projects
Food & BeverageCompleted 2022Baked Snack Production Line Expansion
- Value
- $132M
- Size
- 165,000 sq ft
- Client
- Confidential
Food & BeverageCompleted 2024High-Bay Frozen Distribution Addition
- Value
- $104M
- Size
- 115 ft rack-supported ASRS
- Client
- Confidential
Food & BeverageCompleted 2023Greenfield Beverage Bottling & Distribution Plant
- Value
- $255M
- Size
- 470,000 sq ft · 4 lines
- Client
- Confidential
Your project could be our next story.
Tell us what you are building and the date that matters. In one conversation you will know what it will take to hit it.
- Senior practitioner on the first call
- Confidential by default
- A straight answer, not a sales pitch