SchedolaProject Controls
Services

5 practices.
One line of sight.

All practices & services →
04 · 7 services

Delay & Claims

Forensic delay analysis, time and money entitlement, and independent expert evidence that holds up under cross-examination.

Open
05 · 7 services

Digital Delivery

BIM, 4D and 5D, reality capture and digital twins, wired into the schedule and the budget.

Open
Featured practice

The finish line, visible from day one.

About Schedola

Clarity is a discipline.

Founded by Colins Epie to give every capital project a clear line of sight to its finish.

Overview
Markets

16 markets. One standard of clarity.

Sector fluency, applied with the same discipline everywhere.

Overview
Projects

$19.56B of capital, in plain sight.

60 featured projects across 17 sectors. Every client confidential.

Overview
Insights

Field notes for people who build.

Research, papers and plain-spoken guidance from our practitioners.

Overview
Careers

Do work you can see finished.

Careers for people who would rather know than hope.

Overview
Food & Beverage · ExpansionCompleted 2023

Frozen Dessert Plant Modernization

Three new lines and an automated freezer, installed without one empty space on a summer shelf.

LocationWinnipeg, Canada
ClientConfidential
LocationWinnipeg, Canada
SectorFood & Beverage
Value$185M
Size3 lines · automated freezer store
DeliveryEPCM
Duration28 months
StatusCompleted 2023
Why it mattered

Food and beverage plants live by market windows: peak season, retail launches, distribution contracts. Miss the window and the new capacity waits a year to earn its keep.

The challenge

A food manufacturer modernized one of its largest frozen dessert plants, adding three production lines and an automated cold store.

Any shutdown in peak season meant product missing from stores. Cutovers had to fall in the few low-demand weeks the sales team could spare.

Schedule at a glance

The whole job, on one line.

Start to finish, as the schedule tells it. For work still in progress, the bar moves with today's date.

StartMar 2021
Duration28 months
HandoverJul 2023
Progress—
Protect productionPut equipment on the pathJoin the vendors upPlan trials as real work
How we kept it on course

Our approach, phase by phase.

The same disciplined sequence we bring to every engagement, shaped around what this project needed most.

PHASE 01PHASE 02PHASE 03PHASE 04
PHASE 01Protect production

Shutdowns placed in low-demand periods and planned to the hour with the plant team.

PHASE 02Put equipment on the path

Process equipment tracked from factory slot to setting on its foundation.

PHASE 03Join the vendors up

Line vendors, automation integrators and building trades held on one critical path.

PHASE 04Plan trials as real work

Line trials, food-safety validation and ramp-up scheduled with the same care as construction.

What changed

The difference we made

Measured the only way that matters: did the project land where we said it would.

Result 01Summer output untouched

No production was lost during the peak selling season across the full program.

Result 02Outages on the clock

Every planned shutdown finished inside its window.

Result 03Validation scheduled

Line trials and food-safety sign-offs were built into the logic, not left to the end.

Your project, on schedule

Your project could be our next story.

Tell us what you are building and the date that matters. In one conversation you will know what it will take to hit it.